CORONAVIRUS, EXTENSIONS OF TIME AND TRIAL WINDOWS: THE WHEELS OF JUSTICE MUST BE KEPT TURNING…

In Heineken Supply Chain BV v Anheuser-Busch Inbev SA [2020] EWHC 892 (Pat) Damiel Alexander QC (sitting as a High Court judge) considered issues relating to timetabling and the problems caused by coronavirus.   The problems caused to a party by coronavirus did not justify a postponement of a trial, it did justify a slight re-jigging of the trial date and trial process.

 

“In considering this issue, it is, however, necessary to bear in mind, particularly in current circumstances, that while lawyers are preparing expert evidence, some of their often much less well-remunerated compatriots may be putting themselves and their families at risk in saving lives, working long hours in inhospitable conditions. The guidance to which I have referred strongly suggests that, where it can be safely done and without risks to the integrity of the legal process, the wheels of justice should keep turning at their pre-crisis rate.”

THE CASE

An action in relation to breach of patent relating to a “bag-in-bottle” is listed for five days starting on the 27th April.  It was agreed by the parties that the trial should proceed.   There was an issue as to the start date given a delay in the service of evidence.

THE JUDGMENT

    1. In ordinary circumstances, an application for a two-week extension of time for reply evidence at this stage, coupled with putting back the trial to start outside the trial window, would be hard to justify. However, these are not ordinary times and I must therefore consider whether the reasons put forward for an extension of time and the consequential delay in the start of the trial are justified in the light, particularly, of the current pandemic crisis.
Approach
    1. It is first necessary to consider the principles upon which the court should act in the light of the recent guidance. The general approach to adjournments was recently summarised by Mr. John Kimbell QC, sitting as a Deputy High Court Judge, in Re Blackfriars Limited [2020] EWHC 845, a judgment of 6th April 2020 (albeit in that case the adjournment sought was for a considerable period). At paragraphs [25]-[34] the deputy judge there summarised the guidance given on the approach to dealing with cases in the light of the coronavirus pandemic. That guidance included, amongst other things, the message from the Lord Chief Justice to the Civil and Family Courts published by the Judicial Office on 19th March 2020, which emphasised the importance of doing “what can be done safely”; the first version of the Protocol regarding remote hearings dated 20th March 2020; the further message from the Lord Chief Justice dated 23rd March 2020, concerning court arrangements, which stated that arrangements had been put in place to continue as many hearings as possible remotely. The Deputy Judge summarised the effect of the guidance at paragraph [32] saying:
“There is, in my judgment, a clear and consistent message which emerges from the material I have referred to, the messages that as many hearings as possible should continue and they should do so remotely as long as they can be done safely.”
    1. He also referred to the decision of Teare J on 19th March 2020 in National Bank of Kazakhstan and ors v Bank of New York Mellon and ors, in which an application had been made to adjourn the trial. In that case, Teare J referred to the need to “keep the service of public resolution of disputes going”.
    2. In my view, there is a corollary of that approach, namely that it is desirable where cases have been listed, that attempts are made to keep to the directions timetable where it is realistically possible to do so, without prejudicing safety or risking injustice as a result. It is against that background that paragraph 4 of PD 51ZA should be approached. That provides:
“In so far as compatible with the proper administration of justice, the court will take into account the impact of the COVID-19 pandemic when considering applications for the extension of time, for compliance with directions, the adjournment of hearings and applications for relief from sanctions.”
Extension of time for reply evidence
    1. I turn then to the reasons given by ABI for seeking the extension of time and the consequential delay of the start of trial, which were developed in the evidence of Ms. Macdonald and which I summarise here, dealing first with the expert evidence.
    2. That proposed reply evidence consists of a report of Mr. Stefan Bock, who is based in Switzerland and is currently required to work from home.
    3. First, it is said that Heineken’s expert evidence in chief of Mr. Janssen (to which Mr. Bock’s evidence would reply) is lengthy and concerned primarily with validity of the patents. It was only served by e-mail at about 11 p.m. on the day it was due, which, it is said, meant that work could only start on it after the weekend. However, in my view, that cannot have provided a significant obstacle to ABI dealing with the evidence since it was provided electronically to all concerned. That could not justify an extension of time of the length sought and the point was not really pressed in oral submissions by Mr. Purvis on behalf of ABI this morning.
    4. Secondly, it is said that Mr. Janssen’s reports was marked confidential, which meant that Bird & Bird was not able to share the report with the persons from ABI from whom Bird & Bird received its instructions and that a redacted version was only received some time later. However, there was a confidentiality club in place, pursuant to which the entirety of that report could be seen rapidly by the team at Bird & Bird, by ABI’s counsel, by Mr. Bock and by two individuals at ABI, so that confidentiality, again, cannot justify an extension of the time sought. Again, that point was not pressed.
    5. Thirdly, it is said that there has been disruption as a result of the lockdown. Ms. Macdonald draws attention to the difficulties in preparing reply evidence caused by the impossibility of face-to-face meetings and difficulties in not being able to consider relevant documents when in the same room, as well as the fact that solicitors at Bird & Bird have been working remotely from 18th March. Those difficulties, it is said, are increased by the fact the evidence is both long and develops the case on invalidity in detail for the first time. However, Heineken points out that it is ready to exchange its expert evidence in reply on time, notwithstanding it has been subject to the same general disruption.
    6. Nonetheless, I consider there is some substance in ABI’s point. While it is true that the evidence is not very specific as to why the disruption means that compliance with the original timetable would be impossible, the impact of the crisis has been to require individuals to re-organise aspects of their lives, professional and personal. Preparing documents and evidence has been made somewhat harder in the manner suggested by Ms. Macdonald.
    7. As against that, however, the proposed evidence in question is directed to a relatively straightforward set of patents. It involves consideration of two items of prior art and does not involve co-ordination of the evidence of numerous technical witnesses. Moreover, Mr. Bock’s evidence-in-chief has already considered the prior art in considerable detail with over 30 pages of analysis of one prior art document known as Keisuke and some nine pages of analysis of the prior art known as Richter.
    8. Accordingly, the degree of additional time required for evidence in reply is inevitably more modest and the corresponding need for more time as a result of coronavirus-related disruption is correspondingly limited.
    9. Finally, it is said that one member of the solicitors’ team at Bird & Bird has been ill, having suffered symptoms of Covid-19, and that the solicitor in questions was unable to work on reply evidence for several days. That is, of course, regrettable and fortunately the solicitor concerned is now better.
    10. However, Bird & Bird has a large solicitor team working on this case, which may involve as many as four qualified lawyers as well as counsel. The absence of one member of a substantial and experienced team for a few days since the evidence-in-chief was served on 13th March cannot, in my view, justify an extension in the timetable for service of reply evidence for two weeks. There are other solicitors available and this reply evidence ought in any event to require less involvement of lawyers in drafting since, by this stage, an expert should be up to speed on the manner in which reports need to be prepared and should require less outside assistance in drafting. However, I take the absence of the senior member of the Bird & Bird team into account as justifying a modest element of extension of time in addition to the matters to which I have already referred.
    11. I turn then to the proposed reply evidence of Belgian law. This is said to go to how the court should interpret a judgment of the Belgian court in a dispute between ABI and AFA, the manufacturers of one of the products in dispute. Heineken served a report from its Belgian law expert, a retired judge, Mr. Verougstraete, on 6 March 2020. It was not lengthy (11 pages) of which seven are substantive material. It is said on the behalf of ABI that it has become apparent that it is necessary to refer to arbitral awards between ABI and AFA and that ABI is in the process of contacting AFA to do this.
    12. However, as Heineken submits, this is not said to have been prompted specifically by Mr. Verougstraete’s report. To the extent that these awards are said to have been relevant, Heineken suggests that this would or should have been apparent at an earlier stage, including from Heineken’s defence served in September 2019. I think there is some substance in that point, in that the question of permission from AFA seems to me an independent issue from questions of disruption caused by the current crisis.
    13. Moreover, it is not adequately explained why ABI is only now in the process of contacting AFA, which is more than a month after the original expert report was served on behalf of Heineken. Heineken points out also that ABI has served a substantial brief in proceedings in the Netherlands, of which a significant proportion covers this issue and that that was done in February 2020.
    14. In relation to the evidence of Belgian law, it is also said that there has been general Covid-19-related disruption, with difficulties in working from home and constraints in dealing with the physical documents, as well as the isolation of a partner in the Belgian office of Bird & Bird, who has been assisting on this evidence. It is, however, unclear that this has had an impact on the ability to attend to relevant matters. It has been said that, on occasion, a degree of self-isolation can increase productivity, avoiding some of the distractions of office life. That said, I am here also prepared to accept that the impact of the changes required in professional and personal life merits a degree of accommodation in deadlines, where that can be done without causing undue difficulty.
    15. In considering this issue, it is, however, necessary to bear in mind, particularly in current circumstances, that while lawyers are preparing expert evidence, some of their often much less well-remunerated compatriots may be putting themselves and their families at risk in saving lives, working long hours in inhospitable conditions. The guidance to which I have referred strongly suggests that, where it can be safely done and without risks to the integrity of the legal process, the wheels of justice should keep turning at their pre-crisis rate. It is not unreasonable to expect that lawyers concerned in keeping cases on track may need on occasion to push a little harder to enable that to be achieved. I also bear in mind that the nature of the proposed expert evidence is such that what may be lost in polish as a result of having fewer hours devoted to it by lawyers may be gained in raw authenticity, as well as the fact that a more limited time encourages confining the evidence to that which is truly essential.
    16. Taking all those matters into consideration, I am satisfied that a two-week extension for reply evidence has not been justified on the evidence and that to push the trial back as far as ABI’s original proposal would cause prejudice to Heineken.
    17. However, I am also satisfied that a modest extension of time, to Friday, 17 April, for this reply evidence, principally to take account of the general disruption and distractions caused to some as a result of the coronavirus crisis and the unavailability of one of the solicitors at ABI’s lawyers, would not have a significant impact on the trial or the parties, and would be in accordance with the requirements of Practice Direction 51ZA.
Timing of trial
    1. That then brings me to the consequence of that on the timing of the trial. In this case, given the nature of the issues, although it is desirable for there to be a more lengthy period between reply evidence and skeleton arguments, this is not a case in which it is likely that the contents of the skeleton arguments will significantly develop the case beyond that in the evidence. Although skeletons are bound to be of assistance in drawing the court’s attention to points that are of primary relevance in the evidence, this is not a case in which, for example, it is likely that there will be extensive need for legal submissions in advance of hearing the evidence. That is partly because the focus of this case in the evidence has been on validity and, in particular, arguments of obviousness.
    2. In those circumstances, it does not seem to me unduly prejudicial to either side to require skeletons to be provided on 27th April and for evidence to be heard over three days, starting on 29th April and ending on 1st May.
    3. It is also, in those circumstances, appropriate for their to be a slightly more extended time for provision of closing submissions and I will direct provisionally, subject of further debate at the conclusion of the evidence, that written closing submissions should be provided at the end of Tuesday, 5th and that there be oral closings, which may take the form of a question and answer session, but may be more substantial, depending on the nature of the evidence in question, either on Wednesday, 6th May or Thursday, 7th May, and possibly both, depending on what is required at that time.
    4. The advantage of that course is that it will be possible not only to ensure that there is no clash with the constraints of leading counsel on one side, but that the envelope for the case, at least so far as the parties are concerned, will conclude before the 2020 May Bank Holiday (8th May).
    5. In my view, extending the time for written closings after the evidence is also likely to provide a greater advantage in this case than having a more extended period before the trial commences to develop the arguments that need to be developed.
Further matters
  1. In relation to the other matters as to how argument should go, in my judgment, it is, at the moment, too early to say that no oral opening will be permitted. In my view the trial ought to start with a view to it getting to evidence as rapidly as possible on 29th April, but if it appears as though applications need to be made in relation to any aspect, they can be heard at the commencement of the case and, if absolutely necessary, I would also entertain an application on Tuesday, 28th April, if required, in order that the three-day window can be maintained for completing the evidence in this case.