Main site activities in Harvil Road, Copthall south, north and NSPA areas

Work item: HS2-MW-Ph1-Ar-So-S2-Prog-works-28-09/09/2021

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Harvil Road
Contractor
SCS JV
Type of works
Early construction works, Piling, Utility works / surveys
Estimated Start Date
01/09/2021
Estimated End Date
31/12/2024

What we are doing

Enabling earthwork activities are taking place to make way for the construction the Copthall Tunnel and the Northern & Southern Sustainable Placement Areas. We are also carrying out enabling works in preparation for the realignment of Harvil Road.

We produce maps showing key site activities in the Harvil Road and Copthall area, view details via the pdf document below.

These maps will be updated on a weekly basis.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]