Main site activities in Harvil Road, Copthall south, north and NSPA areas
Work item: HS2-MW-Ph1-Ar-So-S2-Prog-works-28-09/09/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Harvil Road
- Contractor
- SCS JV
- Type of works
- Early construction works, Piling, Utility works / surveys
- Estimated Start Date
- 01/09/2021
- Estimated End Date
- 31/12/2024
What we are doing
Enabling earthwork activities are taking place to make way for the construction the Copthall Tunnel and the Northern & Southern Sustainable Placement Areas. We are also carrying out enabling works in preparation for the realignment of Harvil Road.
We produce maps showing key site activities in the Harvil Road and Copthall area, view details via the pdf document below.
These maps will be updated on a weekly basis.
Download information relating to these works
- Main site activities in Harvil Road and Copthall South areas
- Main site activities in Copthall North and NSPA areas
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]